When planning a production batch, identify which operation must wait for another to finish and which work can run in parallel. Odoo 19 documents dependencies on a bill of materials and the status shown on a work order waiting for a predecessor. The U.S. Government Accountability Office (GAO) schedule guide recommends linking activities in the order work actually requires and justifying date constraints. On a shop floor, that helps the supervisor explain why a particular operation is waiting.
At ToDoOps, we review that sequence with operations teams when implementing Odoo. If the steps are ready but a machine is occupied, see the work centre capacity guide for resource availability and bottlenecks. This guide starts with the relationship between operations within a batch.
Which operations have to wait?
Map one product with the supervisor. For each step, ask what must already be ready and how an operator will know. Dimension inspection can require the cut part, while a packing team might prepare labels ahead of time. Set dependencies where the process requires them. If material availability or a separate quality approval also affects readiness, specify how your team records and verifies it.
In Odoo 19, enable Work Orders and Work Order Dependencies in Manufacturing settings. On the bill of materials, enable Operation Dependencies in the Miscellaneous tab and show the Blocked By field under Operations. Set the predecessor on the row for the operation that waits. Confirm a manufacturing order using that bill and inspect its Work Orders tab. In the documented flow, a waiting order is marked Blocked and moves to To Do once its blocking work orders are complete. Inspect the dependency arrow in Planning by Production and check the work centre view for resource constraints.
Estimate the effect of one delay
Assume a hypothetical batch with cutting, inspection and packing, and an independent label-preparation step. Times are minutes from the start. Set inspection and label preparation as the two predecessors of packing in Blocked By. Label preparation has no predecessor. Assume resources are available and work begins as soon as its requirements are met, with no additional setup or waiting.
| Operation | Prerequisite | Duration in minutes | Earliest finish in minutes |
|---|---|---|---|
| Cutting | Batch start | 30 | 30 |
| Inspection | Cutting complete | 45 | 75 |
| Label preparation | Can start at batch start | 25 | 25 |
| Packing | Inspection and labels complete | 20 | 95 |
Packing waits for the later finish, at minute 75. The batch ends at minute 95. If inspection runs 15 minutes longer and the other assumptions hold, inspection ends at minute 90 and packing at minute 110. Work centre availability can move that date again. The example isolates the effect of the operation link.
Test with one manufacturing order
In a test database, keep cutting open and check the inspection status. Complete cutting and verify that inspection is ready under the configured sequence. Then complete the labels while inspection is still open and check that packing remains blocked until inspection is complete. Compare dates in the production and work centre planning views. Record which version of the bill of materials was tested so changes can be compared with the work instructions. Use the implementation calculators when defining the scope for manufacturing configuration and operator training.
Start with a repeat product where the wait comes up often and map it with the team that records each operation. Visit ToDoOps, compare implementation scope, or discuss your manufacturing workflow.
Sources
Odoo 19 documentation
Work order dependencies on a bill of materials, status changes and linked work orders in planning views.
U.S. Government Accountability Office
Schedule Assessment Guide GAO-16-89G, Best Practice 2 on sequencing activities and explaining constraints.