When a project team finishes a stage, check what the contract requires as evidence of acceptance before posting the invoice. Odoo 19 documentation explains how reaching a project milestone updates the delivered quantity on the sales order line and how invoicing is initiated from the order. The IFRS Foundation’s overview of IFRS 15 ties revenue recognition to satisfying a performance obligation. Keep the acceptance evidence, invoice status and collection status visible to the teams that own them. Review the accounting treatment with your finance team.
ToDoOps implementation helps align the handoff between project management and invoicing. The Odoo project management guide covers the wider task and cost workflow. This guide works through the evidence and amount for the next milestone invoice.
Define what qualifies a milestone for billing
Give each stage a reviewable deliverable, a named reviewer and an acceptance rule. The deliverable could be an approved design or a set of configured processes that pass a defined acceptance test. Decide how to deal with a partial acceptance or unresolved exception. Before posting, match the accepted deliverable to the agreed sales order line and percentage.
In the documented Odoo 19 flow, configure a service product with the Based on Milestones invoicing policy. Assign the milestone to the sales order item and specify the share of the ordered quantity. When you mark it Reached, the delivered quantity on the order updates. Create the draft invoice separately from the sales order and review it. If the project comes from a template, check the percentages on the new project before billing.
Reconcile the amount of the next invoice
Consider a hypothetical service line of SAR 100,000 before tax, with an ordered quantity of one. Assume no down payments, credit notes or other adjustments, and that the first accepted stage has been fully invoiced.
| Deliverable | Share of service line | Value before tax | Example status |
|---|---|---|---|
| Design approval | 25% | SAR 25,000 | Previously invoiced |
| Initial rollout accepted | 45% | SAR 45,000 | Eligible for next draft |
| Closeout accepted | 30% | SAR 30,000 | Awaiting acceptance |
| Total | 100% | SAR 100,000 | Full service line |
After acceptance of the first two deliverables, the delivered quantity is 0.70, representing SAR 70,000. Subtract the 0.25 already invoiced. The next draft should reconcile to a quantity of 0.45 and SAR 45,000 before tax under these assumptions. Retain the earlier invoice reference beside the new acceptance evidence. On orders with several lines, reconcile against the correct item and price. Use the implementation calculators when estimating the scope of a project, sales and accounting rollout.
Test the controls before you post
- Complete or cancel the tasks linked to a test milestone. Odoo documents that linked tasks finishing as Done or Cancelled can mark a milestone Reached. Have the reviewer check the separate client acceptance evidence before generating the draft.
- Test acceptance of the initial rollout while final closeout remains under review. Check the new draft against the contract and the posted invoice for the first stage. Confirm that previously billed amounts do not recur. Explain any difference from the expected share.
- Introduce a documented scope change. Check whether it affects the existing line or creates a separate one. Trace the amendment, each invoice and its collection status independently.
Agree the handoff with both teams
Choose one deliverable and follow it from its acceptance record to the correct sales order line and draft invoice. Start with ToDoOps, compare implementation scope, or discuss the billing workflow.
Sources
Odoo 19 documentation
References for milestone invoicing, linked sales order items, delivered quantities and the status of linked project tasks.
IFRS Foundation
The public summary explains how revenue recognition is tied to satisfaction of performance obligations. IFRS 15 overview.